September Achievements

  • Commencement of Sheetpiles
  • Continued excavation
  • Commencement of Tie-Backs

Activities in the Month of October 

  • Three Piling rigs will drive sheet piles, creating the outline of the development
  • Excavation and hauling of soil will continue
  • Tie-back drilling and grouting

Activities in the Month of November

  • Continue soil excavation
  • Complete Sheet pile installation
  • Start augur pile installation for the foundations