Navy GAF (General Administration Facility) Updates

Navy GAF (General Administration Facility) Updates

September Achievements

  • Continued dewatering (average flow is 19,490 gallons per hour)
  • Continued excavation (total of 36,000 cy exported as of September 28)
  • Completion of Tie-Backs
  • Steel, Precast and Curtain Wall material released for procurement.

Activities in the Month of October 

  • Plywood substrate for waterproofing at PCH sheet pile walls 
  • Excavation and hauling of soil will continue currently at -10′
  • Dewatering will continue additional interior and exterior wells being installed
  • H piles to be installed at PCH for concrete trucks and assist crane
  • Turner Trailer to be installed at Harbor Drive

Plans for November

  • Test Piles (Auger Cast), total of 982 permanent ACP to be installed
  • Nearing excavation completion currently anticipated for December 4, 2018